An operating sour gas plant needed a new centrifugal gas compressor—and the job came to us.

For this project, our role was to provide FEED and detailed engineering and procurement to support the installation of a new 2500 HP Elliott compressor c/w lube oil console skid, nitrogen generator package, and gas seal system. The project also required the installation of utility systems including a dry air system for the nitrogen package, an electric motor purge system with blower and ductwork, and a variable frequency drive in a self-contained building with HVAC.

With the congested and confined work area, we had to get creative. To allow compressor installation and keep the utility systems online, process and utility tie-ins to the existing facility were installed during a plant turn around.

With flexibility and inventiveness, our team tackled this project and met the complex needs of the client without delay or difficulty.

Location
Alberta, Canada
Offices