The Apache Junction Sewer District (AJSD) needed a clear path to grow its Water Reclamation Facility (WRF) from 3 million gallons per day (MGD) to a projected buildout of 26 MGD. Building on the 2019 WRF Master Plan, we developed a detailed phasing plan for the 90-acre (36-hectare) site that aligns with AJSD's water quality and reuse goals, including existing and planned recharge basins.
Through concept and technology workshops with AJSD, we delivered a final phasing plan in eight months, complete with site layouts, a cost estimate, and interim capital improvements to bridge the gap before the first expansion.
The plan transitions treatment from the existing Biolac system to a membrane bioreactor (MBR) process across four phases, adding primary clarification, anaerobic digestion, and solids dewatering. MBR was chosen for its high-quality effluent and smaller footprint, preserving room for future recharge basins and supporting AJSD's long-term reuse strategy, from groundwater recharge to eventual direct potable reuse (DPR).
To limit upfront investment, Phase 1 (3.5 MGD) runs the new MBR system in parallel with the existing Biolac plant. We modeled wastewater characteristics using BioWin™, accounting for shifting septage volumes and rising flows as development continues.
Our scope also covered capacity planning for secondary treatment, filtration, disinfection, biosolids, and reuse management, plus cost estimates and capital improvement planning.
With major growth expected over the next two to 20 years, the challenge was right-sizing expansion while keeping DPR goals in view. The plan balances near-term projects with the Phase 1 upgrade, allowing partial renovation of the Biolac process so it can stay in service another decade.
" }