Chisholm View Wind Farm

45,000 acres of clean power

  • 235

    MW

  • 45K

    Acres

  • 140

    Turbines

  • Garfield and Grant Counties, Oklahoma

    Garfield and Grant Counties, Oklahoma

Helping bring new wind power and millions of dollars in revenue to Kansas and Oklahoma

North to Wichita or south to Oklahoma City, this new wind farm is delivering clean power from one of the most energetic wind development sites in Oklahoma. Enjoying strong community support, the development–which uses less than 2 percent of its site–brings $5 million every year to the farming communities of Northern Oklahoma.

We provided interconnect engineering services for the developer and supported negotiations for the 138 kilovolt interconnect with Oklahoma Gas & Electric. Stantec also designed the 345 to 34.5 kilovolt collector substation including site work, physical geographic information system switchgear and electrical design, procurement and construction specifications, testing procedures, and operations and maintenance manuals. Design of the collector system included system studies, 34.5 kilovolt feeder design, equipment and construction specifications and testing procedures, control system including communication, Supervisory Control And Data Acquisition (SCADA), protective relay setting, and testing.

At a Glance

Offices

We're better together

  • Become a client

    Partner with us today to change how tomorrow looks. You’re exactly what’s needed to help us make it happen in your community.

    Contact Us
  • Design your career

    Work with passionate people who are experts in their field. Our teams love what they do and are driven by how their work makes an impact on the communities they serve.

    Join the Team
End of main content
To top